Lichfield STW – Enhancing Effluent Quality for WFD Compliance

Project Overview

CLient

Severn Trent Water Ltd

Project Name:

Lichfield STW – Enhancing Effluent Quality for WFD Compliance

Objective:

Improve effluent quality and meet AMP7 Water Framework Directive (WFD) regulatory standards.

Principal Contractor:

FLI Water

🔍 Project Overview:

FLI Water, in partnership with Glasswell & Last (G&L), has been commissioned by Severn Trent Water to carry out a series of upgrades at Lichfield STW aimed at meeting WFD permit tightening and improving overall treatment efficiency.

Scope of Works:

  • Construction of a new chemical dosing bund and chemical delivery area

  • Installation of a new wet well and humus sludge return pumping station

  • Construction of new ducting routes and duct boxes

  • Excavation and installation of new sludge pipework

  • MCC Kiosk fit-out and integration with civil infrastructure

Temporary access and site facilities

Latest Update:

  • Chemical Dosing Bund: 2 of 3 pours now completed, with formwork being reset for the final section.

  • Wet Well Construction: Base and two concrete rings completed, next two positioned and pour planned.

  • Ducting: 62m installed following new design, with concrete capping in required areas.

  • Sludge Pipework: Excavation ongoing, approx. 55m remaining.

  • MCC Kiosk: Final fit-out by G&L nearing completion.

  • Temporary Car Park: Fully completed and in use.

  • Deliveries: Various stock items have been received on site.

This project highlights the importance of early coordination, flexible problem-solving, and collaborative delivery in complex live site environments.