Bredon STW – Green Recovery WINEP Upgrade

Project Overview

CLient

Severn Trent Water Ltd

Project Name:

Bredon STW – Green Recovery WINEP Upgrade

Objective:

To deliver key environmental improvements at Bredon STW as part of Severn Trent’s Green Recovery programme and to meet tighter Water Industry National Environment Programme (WINEP) phosphorus discharge permits.

Principal Contractor:

FLI Water

Scope of Works:

  • Construction of a new ferric dosing system and chemical delivery area

  • Installation of a recirculation pumping station wet well and internal benching

  • Cross-site ductwork and pipework to support improved treatment processes

  • Biofilter mechanical mobilisation for enhanced filtration and process performance

Update – October 2025

The project is progressing well:

  • Chemical dosing slab construction and excavation completed

     

  • Dosing plant equipment delivered and successfully installed

     

  • Recirculation pumping station wet well constructed with internal works

  • Excavation of the site-wide pipework run is complete and final pipework connections are underway

Next Steps:

  • Completion of all pipework and testing

  • Mechanical installations in the chemical dosing area

  • Installation of footpaths, bollards, and access enhancements

  • Commencement of manhole ring installation

This project plays a key role in improving effluent quality and delivering long-term environmental benefits under the Green Recovery scheme.