Coaley STW – WFD Upgrade

Project Overview

CLient

Severn Trent Water Ltd

Project Name:

Coaley STW – WFD Upgrade

Objective:

Deliver key wastewater treatment upgrades to achieve tighter regulatory standards set under the Water Framework Directive (WFD)

Principal Contractor:

FLI Water

Scope of Works:

FLI Water was appointed to design, construct, and commission upgrades at Coaley STW. The aim is to improve phosphorus removal performance and meet tightened discharge permits.

Key project scope includes:

  • New Ferric Dosing System and chemical delivery bund
  • New Tertiary Solids Removal (TSR) feed pumping station
  • Installation of TSR plant
  • New Final Effluent (FE) interception chamber
  • Cross-site ductwork and pipework installation

Progress Update:

  • Successful tandem lift and placement of the new chemical dosing equipment
  • Completion of the chemical bund area to house installed units
  • Ongoing pipework installation linking the recirculation pumping station, TSR, and interception chamber

 

Looking Ahead:

The coming weeks will focus on advancing mechanical installations, completing ductwork, and progressing infrastructure around the dosing area.


FLI Water continues to deliver with precision and care, supporting Severn Trent’s environmental goals and regulatory commitments.